Project Overview
The project will consist of upgrades and improvements to the McKinley Stormwater Pump Station, located along Maple Trail Woods.
This pump station is critical to stormwater relief efforts and the improvements will provide backup pumps, power, and improved controls and monitoring.
The City of Elmhurst held a virtual public meeting to provide information on construction to improve the McKinley Stormwater Pump Station.
If you have questions, please contact Tom Foley of Clark Dietz, Inc. at tom.foley@clarkdietz.com.
Latest Update
Updates are provided every 2 weeks in conjunction with construction progress meetings.
Last Update: 3/24/2023
Next Update: Week of 4/3/2023
Construction has begun at the McKinley Lift Station. Erosion control measures have been installed and construction equipment is arriving on site.
Over the next two weeks, a stone construction entrance path will be installed between the pump station and the south end of Sunnyside Avenue. This work is anticipated to take 3 days, weather permitting. Following installation of the access path, excavation near the station will begin for the construction of the new pump station expansion.
Impacts